Poch develops the entire Engineering from the design, to the start-up of a high voltage substation.
Description of the Project:
Agrocomercial AS develops an industrial complex in the region of Atacama for exporting pork. This project contemplates in the first stage the Slaughter of 500 pigs per hour to finally get to 1000.
The industrial complex contemplates a total investment of US$ 600M, considering a marine terminal, maternity section, breeding wards, food plant, slaughter plant, digester plant and treatment plants. In addition, it includes medium voltage transmission lines, power generator plant and electrical substation.
Regarding the electrical provision, a 220KV transmission line and a substation with 2 50MVA transformers are included for the entire complex.
Our importance:
Poch provides the Engineering of the civil, structural and electrical specialties, the project management and coordination, the supervision and technical inspection and the start-up of the facility.
Additionally, it carries out the connection management to the CIS (Central Interconnected System).
Essential benefit:
This facility, key for the electrical provision needs of the complex integral project, was carried out respecting the estimated time and budget allowing Agrocomercial AS to progress in its expansion plan.